March 23, 2016

Proposed Pontoon Update

Planning consent for this development was  granted by Highland Council in January 2017.

31st January 2018 update: the order for our structures (3 x 10m  pontoons and bridge) was placed with Gaelforce Engineering at the end of  October 2017 and is scheduled for delivery to Dunvegan March/April this  year. For those of you unfamiliar with the area, the pontoons will be  located approximately 200m beyond the fishing pier in the direction of  the hotel and adjacent to the 6 visitor moorings.  All being well, it  should be fully operational beginning of May.

We are of course grateful to everyone who has contributed to this project.

Iain  Chairman, loch Dunvegan Moorings Association